Client: Horizon Jebel Ali Terminals LLC
Project Name:
• FOC Cable Interconnection between Terminals.
• Construction of Chemical Storage Shed.
Year of Construction: 2019-2020
Type of contract: Main Contract
System: Chemical Storage Shed Construction
Fiber Optic Cabling Structural: Structural Works for chemical Storage Shed Construction using standard Beams and Columns with authority approvals
Civil: Excavation concrete foundation works for chemical shed, vacuum machine excavation for cabling
E&I: FOC cabling & OFC Splicing between terminal 1 and 2 with all authority approvals.
Authority Approvals: JAFZA, RTA, DEWA, ETISATAT, DU, TRAKHEES, DCD, NOC’s
]]>

Client: Star Energy Oil Tanking
Project Name: Marine Loading Arm (MLA) & Gangway System for Berth №s 8 & 9
Year of Construction: 2019-2020
Type of contract: EPC
System: Marine Loading Arms (MLA)
Mechanical: Detailed Engineering.
Replace existing marine loading arms at berth 8 and 9 with higher Capacity MLAs (05 №s). Berth Piping, Pig launcher piping, Tie in connections, Hydraulic Power Units, Hydraulic SS Tubing Network.
Electrical & Instrumentation: Power/control cabling from Substation MCC to Berth Equipment’s – HPU power packs, Gangways, Control/RIO panels, Area Lighting. HDGI cable trays, Ex-proof panels/junction boxes, Light Fixtures. Integration & interfacing of new MLAs with existing SCADA system.
Structural: Structural steel design calculation, Gangways steel structure installation, Access platforms, Crossover platforms, Pipe support structures.
Civil: Site survey, Construction of foundations for MLAs, Gangway towers, Pipe supports & pig launchers. Construction of HPU Sheds
Shutdown: Sequential shutdown of MLAs for uninterrupted operation of berths.
Approvals Obtained: Trakhees (EHS & CED), Abu Dhabi Civil Defense (DCD), JAFZA, Tanker Berth Permits, DP world.
]]>
Client: Emirates Petroleum Products Company L.L.C (EPPCO)
MAJOR PROJECTS: Underground Diesel Gas Oil (DGO) Pipe Line Project-Terminal 1 Upgradation of Tanker Truck Loading Rack (TTLR) Piping System.
Above Ground Fire Water Piping Ring in Terminal 1 – JAFZA
Year of Construction: 2018-2020
Type of contract: EPC Contractor
Systems: Diesel Gas Oil (DGO) Piping: Tanker Truck Loading Rack (TTLR) : Pumping Station Power/control Cable Network : Firewater Network (Sea water Application) : Terminal Communication/CCTV system : Instrumentation and Control
MECHANICAL: Detailed Engineering & Stress Analysis. Underground 16” DGO pipeline from Berth to Terminal 1 with Tie ins. Aboveground 14” API 5L Piping (1 KM) with Internal Fusion Bond Epoxy Coating & outer Painting. TTLR piping upgradation for product segregation. Structural Steel supports for the pipeline, Valve Operating Platforms & Crossover platforms.
ELECTRICAL: MCC to Jet Fuel Pumping station power/control cabling, Inline heat shrink cable jointing, Optical Fiber Cabling/Splicing, OTDR testing, Local control stations, TTLR control panel upgradation.
CIVIL: Pneumatic/Suction Excavation in explosive or hazardous atmosphere for underground piping/cabling. Foundations for pipe supports, operating platforms. Construction of Valve chambers/Manholes for underground services.
SHUTDOWN: Shutdown, Draining & Isolation of Berth to Storage Terminal Loading Pipeline for tie in with the new pipeline. Jet Fuel Pumping station MCC shutdown for inline cable joints.
APPROVALS OBTAINED: Trakhees (EHS & CED), Abu Dhabi Civil Defense (DCD), JAFZA
]]>
Client: Abu Dhabi National Oil Company (OIL TECH)
Project Name: MULTIPLE PROJECTS – Fuel Storage and Distribution Terminals / Depots & Fuel stations
Year of Construction: 2016-2020
Type of contract: Main Contract
System: Fuel Intake Piping from Berth to Tank farm Terminal Truck Loading Bays Marine Loading Arm Overhauling Fuel Station – Full Fuel System with Dispensers Jacketed Fuel Piping Flow Metering System
Tank Gauging Instrumentation and Control Mechanical: Diesel Piping, Gasoline Piping, LPG Piping, Jacketed Fuel Piping, Floating Jetty Dispenser and its Piping works.
Tanks: Two Hour Fire Rated Tanks, Single Skin & Double Skin Storage Tanks for Fuel Stations.
Structural: Loading bay platforms, Pipe Supports.
Civil: Fuel Station Tank Foundations, Dispenser islands.
Electrical &Instrumentation: Tank Gauging System, Flow Metering, Flow Computing, Filling station, Instrumentation and Control system, Tank Farm MOV Automation, Truck Loading Automation.
Shutdown Works: Marine Loading Arm Installation with Sea Movement. LPG Tank Header Line.
Overhauling & Maintenance: Marine Loading Arms overhauling and Annual Maintenance for Sharjah Depots and Hamriya Depots.

Client: Emirates General Petroleum Corporation (Emarat)
Project Name:
Year of Construction: 2010-2020
Type of contract: Main Contract
System: Tank Roof replacement and Floating roof Installation
Tanks Mechanical: Replace full roof of 40 meter diameter fuel storage tank. Replace damaged shell walls, Install floating roof for 2 storage tanks. Piping works in tank farm and pump station. Replacement of 36-meter dia tank annular plate, Repair works on 25-meter dia, 15-meter height fuel storage tank including floating deck. Under Ground Diesel line leak detection and repair works from berth to terminal.
Structural: Tank platforms and staircase, roof supports, valve operation platforms. Painting internal and external of 3 storage tanks including internal roof.
Civil: Excavation and office modification works, Pipe Civil Foundation, Valve Pit Construction.
Electrical & Instrumentation: Radar Tank Gauging system relocation with underground cabling Power, communication and optical fiber cabling network up gradation.
Tank Hydro test: Carry out hydro test using sea water for 3 no’s of big fuel storage tanks with all authority approvals.
]]>